The requirement
Your block gets a letter from A to P under AS 2870 before you build (NCC 2025, Housing Provisions clause 4.2.2). The letter says how much the ground will move. Footing and slab concrete must reach at least 20 MPa (N20) (clause 4.2.10). The exact grade and cover for your job come off your engineered plan.
Why does the ground move? Clay swells when it gets wet and shrinks when it dries. That movement is what cracks slabs and footings. AS 2870 is the Australian rule book for house footings and slabs.
You have two legal paths. Classify the site, then follow the Housing Provisions Part 4.2 build rules, which mirror AS 2870. Or design the whole footing straight to AS 2870. Either way, the classification comes first. It sets everything downstream.
The site classes. A soil test on your block sets the letter. Here’s what each one means in plain words:
| Class | What the ground does |
|---|---|
| A | Mostly sand or rock. Little or no movement. The calmest. |
| S | Slightly reactive clay. A bit of movement. |
| M | Moderately reactive. More movement. |
| H | Highly reactive clay. A lot of movement. |
| E | Extremely reactive. Moves the most. |
| P | “Problem” site — soft or loose soil, landslip, mine subsidence, or reactive/collapsing fill. Always needs an engineer. |
You don’t pick the class yourself. A soil tester or engineer bores the block and tells you. Your job is to build to the class they give you.
- 1 footing
- 2 reinforcement
- 3 ground
Prepping the trench. Once the footing is designed, clause 4.2.3 tells you how to get the ground ready:
- Strip the topsoil. That’s the layer with grass roots in it.
- Keep the trench clean. No loose earth, tree roots, mud or debris in the bottom when you pour.
- Keep the base roughly level. It may fall up to 1:40 so water can drain away.
- On loose sand, or ground that washes away easily, the footing bottom must sit at least 300 mm below the finished ground level.
The grade and the cover. Housing Provisions clause 4.2.10 sets a floor. Footing and slab concrete must reach at least 20 MPa (grade N20) at 28 days. Never pour below that. Above the floor, the grade for your site class comes from AS 2870. Reactive sites need more. The cover over the steel comes from AS 3600. It changes with how exposed the concrete is. So the exact numbers come off your engineered plan, or from your engineer. If a mate quotes a grade off the top of his head, check it against the plan before you order the truck.
Work it out by hand
The trench prep is code. The volume of concrete you order is just maths, and it feeds straight into the calculator. Say you’ve got a strip footing to pour. These are example numbers, not code minimums. Your real sizes come off the plan:
- Total length of trench: 24 m
- Trench width: 0.45 m
- Footing depth: 0.5 m
Volume = length × width × depth.
24 × 0.45 × 0.5 = 5.4 m³.
So you’d order about 5.4 cubic metres. Then add a bit for spillage and an uneven trench bottom. Most blokes tack on 5 to 10 per cent. Swap in your own lengths and the calculator does the sum for you.
Do it in 5 seconds
Related
- Part of the NCC rules for Australian chippies — the pillar guide, with the state-by-state adoption tracker.
- Digging posts instead of a strip footing? See concrete for post holes.
- Working out the pour? Use the concrete volume calculator for slabs & footings.
Sources
- NCC 2025, ABCB Housing Provisions Standard, Part 4.2 “Footings, slabs and associated elements” — site classification to AS 2870 (clause 4.2.2) and excavation rules including the 1:40 fall and the 300 mm depth on loose/erosion-prone sites (clause 4.2.3), and the minimum 20 MPa (N20) concrete strength (clause 4.2.10). Confirm at ncc.abcb.gov.au.
- AS 2870 — Residential slabs and footings — sets the site classes (A to P) and the concrete strength grade for each class. The grade must be read from AS 2870 or your engineered plan, not assumed.
- AS 3600 — Concrete structures — sets the concrete cover over the steel, which depends on the exposure. Check the cover in AS 3600 or on your plan.